.TRS_Editor P{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor DIV{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor TD{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor TH{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor SPAN{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor FONT{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor UL{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor LI{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor A{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋体;font-size:10.5pt;}

  本报讯为合理开发利用尼洋河水能资源,增加西藏藏中电网电力供应,满足用电增长需要,改善当地居民生产生活条件,促进民族地区经济和社会发展,2014年7月12日国家发展改革委以发改能源[2014]1636号文对尼洋河多布水电站可行性研究报告进行了批复,同意建设多布水电站。

  电站安装4台3万千瓦灯泡贯流式水轮发电机组,总装机容量12万千瓦,年均发电量5.06亿千瓦时。

  该项目由中国国电集团公司、西藏天峰能源开发有限公司、国电四川电力股份有限公司分别按51%、30%和19%的比例共同出资组建的国电西藏尼洋河流域水电开发有限公司负责建设和管理。该项目安排中央预算内投资定额补助12.13亿元,占总投资的45%。(吴坤峰)

Baidu
map